Week Reports
09/02 - 15/02
- State of the art on electric vehicles, energy sources, energy management architectures, DC/DC converters and modeling of Power Converters
16/02 - 22/02
- Construction of the personal website
- First meeting with the Co-Supervisor
23/02 - 01/03
- First meeting with the Supervisor
- Redifinition of some points of the work
02/03 - 08/03
- Construction of the mathematical model of a boost converter
- Simulation of the converter using different software
09/03 - 15/03
- Design of a closed-loop voltage controller using MATLAB and SIMULINK
- Simulation of the closed-loop voltage controller using PSIM and SIMULINK
16/03 - 22/03
- Design of a dual voltage and current controller using MATLAB and SIMULINK
- Simulation of the dual voltage and current controller using PSIM and SIMULINK
- Loss analysis and sizing of all the components of the system of the four-phase converter
23/03 - 29/03
- Continuation of the loss analysis and sizing of all the components of the system
30/03 - 05/04
- Third Meeting with the Supervisor (Italy)
- Redefinition of some points regarding the controllers
06/04 - 12/04
- Construction of a model of a two-phase boost converter using MATLAB/SIMULINK
- Simulation and validation of the model
13/04 - 19/04
- Construction of a current-voltage controller for a two-phase boost converter using MATLAB/SIMULINK
20/04 - 26/04
- Continuation of the construction of a current-voltage controller for a two-phase boost converter using MATLAB/SIMULINK
- Simulation and validation of the controller
27/04 - 3/05
- Second meeting with Co-Supervisor (Portugal)
- Evaluation of the work done while studying abroad
4/05 - 10/05
- Break (Queima Das Fitas do Porto 2014)
11/05 - 17/05
- Construction of a model of a four-phase boost converter using MATLAB/SIMULINK
18/05 - 31/05
-Study, design and simulation of a sliding mode controller for a boost converter
-Study, design and simulation of a sliding mode controller for a two-phase boost converter
-Study, design and simulation of a sliding mode controller for a four-phase boost converter
1/06 - 14/06
-Study of a new power converter simulation tool
-Implementation of the converters using this new simulation tool
15/06-30/06
-Simulation and results of the converters using both MATLAB and the new power converters simulation tool
1/07-15/07
-Study, analysis and simulation of the switches losses for each power converter
16/07-31/07
-Simulation and result analysis of the global efficiency of each power converter when introducing the switches losses
1/08 - 31/08
-Writing of the final document